International partners agree on security guarantee mechanism for Ukraine Zelenskyy names NATO membership as the best security guarantee for Ukraine at 'Coalition of the Willing' meeting Ukraine to receive €90 billion in EU aid: results of the Berlin meeting Situation in occupied Crimea: Simferopol residents rush to stock up on food and fuel following Kerch Bridge attacks Road sign R9-4: what the 'thumbs up' symbol means Name Day on November 27: Who Celebrates Children's Day in Ukraine: New Celebration Date Oleksandr Usyk shares details of personal conversation with Cristiano Ronaldo Group of citizens in Kovel prevents detention of a draft evader Student-Teacher Romance: How It Changed a British Man's Life International partners agree on security guarantee mechanism for Ukraine Zelenskyy names NATO membership as the best security guarantee for Ukraine at 'Coalition of the Willing' meeting Ukraine to receive €90 billion in EU aid: results of the Berlin meeting Situation in occupied Crimea: Simferopol residents rush to stock up on food and fuel following Kerch Bridge attacks Road sign R9-4: what the 'thumbs up' symbol means Name Day on November 27: Who Celebrates Children's Day in Ukraine: New Celebration Date Oleksandr Usyk shares details of personal conversation with Cristiano Ronaldo Group of citizens in Kovel prevents detention of a draft evader Student-Teacher Romance: How It Changed a British Man's Life

Experts predict multi-year restoration for Crimean Bridge following latest attack

🚌 Transport 1 min read 👁 0

The New York Times analysts suggest that repairing the damaged Crimean Bridge infrastructure could take years due to the complexity of its design.

Experts predict multi-year restoration for Crimean Bridge following latest attack🚌Transport

Photo: UNIAN

Key points

  • Restoration could take approximately two years
  • The destroyed arch is a unique structural element
  • Russia is deploying auxiliary vessels for cleanup operations

Engineering challenges

The recent damage to the Crimean Bridge, resulting from an attack, differs significantly from previous incidents in terms of scale. According to international engineering experts, restoring the facility could take several years, as the destroyed 230-meter steel arch is a unique component that requires a complex manufacturing cycle.

In peacetime, the assembly and installation of such a structure alone took about two years. Experts emphasize that even the process of clearing debris from the Kerch Strait is a technically demanding task, further complicated by the need to maintain shipping lanes in the channel.

Logistical impact

Despite Moscow's significant efforts to expedite repairs, the current situation is far more challenging than the attacks of 2022 and 2023. While previous repairs took several months, the current damage to critical structural nodes requires massive resources.

The Crimean Bridge remains a vital artery for supplying the peninsula, as alternative land routes through occupied territories are under constant threat. Currently, the Russian side has already begun deploying auxiliary vessels to the site to conduct emergency recovery operations.

Source UNIAN — unian.ua/war/shchob-vidnoviti-kerchenskiy-mist-rosiji-potribno-shch… ↗